Jenny Soo <br /> May 8,2015 <br /> Page 5 <br /> Project Mitigation Measures <br /> The 2014 Addendum identified 10 mitigation measures in the Supplemental EIR that were applicable to <br /> the 2014 project. While the 2015 project's reduced unit count would reduce the intensity of some of the <br /> project's potential environmental impacts,the Supplemental EIR mitigation measures identified in the <br /> 2014 Addendum would still be applicable to the 2015 project. Each mitigation measure and its <br /> applicability to the 2015 project are discussed below. <br /> Air Quality <br /> Mitigation Measure 4.B-la:Prior to the issuance of a grading or building permit,whichever is sooner,the <br /> project Applicant for a potential site for rezoning shall submit an air quality construction <br /> plan detailing the proposed air quality construction measures related to the project such <br /> as construction phasing,construction equipment,and dust control measures, and such <br /> plan shall be approved by the Director of Community Development. Air quality <br /> construction measures shall include Basic Construction Mitigation Measures(BAAQMD, <br /> May 2011)and, where construction-related emissions would exceed the applicable <br /> thresholds,additional Construction Mitigation Measures shall be included on all grading, <br /> utility, building, landscaping, and improvement plans during all phases of construction. <br /> Similar to the 2014 project,the 2015 project would result in construction emissions from heavy-duty <br /> construction equipment,trucks,worker vehicle emissions,and fugitive dust emissions, albeit to a lesser <br /> degree than the 2014 project. Such emissions could contribute to cumulatively considerable net <br /> increases in air pollutants for which the project region is in nonattainment. However, implementation of <br /> Mitigation Measure 4.B-la from the Supplemental EIR would ensure that impacts from fugitive dust and <br /> other construction emissions(air pollutants,toxic air contaminants)would be less than significant and <br /> would adhere to the BAAQMD's requirements. Furthermore, Illingworth& Rodkin, Inc.who assessed <br /> the potential of the 2014 project to expose residents to unhealthy air pollutant or toxic air contaminants <br /> (TACs), concluded in an letter dated April 27, 2015 that, similar to the 2014 project,the 2015 project <br /> would not expose residents to TAC levels above the community risk threshold recommended by the Bay <br /> Area Air Quality Management District. As such, air quality impacts related to the 2015 project would <br /> continue to be less than significant. <br /> Biological Resources <br /> Mitigation Measure 4.0-la:Pre-construction Breeding Bird Surveys. The City shall ensure that prior to <br /> development of all potential sites for rezoning(Sites 1-4,6-11, 13, 14,and 16-21)and <br /> each phase of project activities that have the potential to result in impacts on breeding <br /> birds,the project Applicant shall take the following steps to avoid direct losses of nests, <br /> eggs, and nestlings and indirect impacts to avian breeding success: <br /> • If grading or construction activities occur only during the non-breeding season, <br /> between August 31 and February 1, no surveys will be required. <br />