<br />April 1, 2025 52 City of Pleasanton/GreenWaste Recovery, LLC <br />A. Prior to assessing Liquidated Damages, the City shall give Contractor written notice of its intention to do so. 1999 <br />The notice shall include a brief description of the incident(s)/non-performance giving rise to the damages. 2000 <br />B. The City shall assess Liquidated Damages and provide Contractor with a written explanation of its 2001 <br />determination for each incident(s)/non-performance. The City Contract Manager may, at their sole discretion, 2002 <br />impose such Liquidated Damages for each Day or incident of non-performance with the Agreement. 2003 <br />C. Contractor shall pay any Liquidated Damages assessed by the City within thirty (30) Days after they are 2004 <br />assessed. If they are not paid within the thirty (30) Day period, the City may treat such failure as an Event of 2005 <br />Default subject to the remedies in this Article. 2006 <br />11.10 Excuse from Performance 2007 <br />In the event that a Party is prevented from performing all or some of its obligations under this Agreement by an 2008 <br />Uncontrollable Circumstance, it shall not constitute an Event of Breach or Default of this Agreement, so long as the 2009 <br />Party in good faith has used its best efforts to perform its respective obligations. The Party claiming excuse from 2010 <br />performance shall, within five (5) Days after such Party has notice of the effect of such cause, give the other Party 2011 <br />notice of the facts constituting such cause and asserting its claim to excuse under this Section. Specifically, such 2012 <br />information shall include the following: 2013 <br />A. The Uncontrollable Circumstance and the cause thereof (to the extent known); 2014 <br />B. The date the Uncontrollable Circumstance began, its estimated duration, and the estimated time during which 2015 <br />the Party’s performance of its obligations hereunder will be delayed; and, 2016 <br />C. Potential mitigating actions that might be taken by either Party and any areas where costs might be reduced 2017 <br />and the approximate amount of such cost reductions. 2018 <br />In the event that either Party validly exercises its rights under this Section, the Parties hereby waive any claim against 2019 <br />each other for any damages sustained thereby. 2020 <br />Labor unrest, including, but not limited to, strike, work stoppages or slowdown, sick-out, picketing, or other 2021 <br />concerted job action conducted by Contractor’s employees, directed at Contractor, or a contractor or supplier of 2022 <br />Contractor, is not an Uncontrollable Circumstance and will not excuse performance, and Contractor will be obligated 2023 <br />to continue to perform in accordance with this Agreement. 2024 <br />11.11 Right to Demand Assurances of Performance 2025 <br />If the City believes in good faith that Contractor’s ability to perform under this Agreement has been placed in 2026 <br />substantial jeopardy, the City may require that Contractor provide reasonable assurances that none of the events 2027 <br />listed below will prevent Contractor from timely and proper performance of its obligations under this Agreement. 2028 <br />Such events include, but are not limited to: 2029 <br />A. Contractor or an Affiliate is the subject of any labor unrest including work stoppages or slowdown, sick-out, 2030 <br />picketing, or other concerted job action affecting this Agreement; 2031 <br />B. Contractor or an Affiliate appears, in the City’s reasonable judgment, unable to regularly pay its bills as they 2032 <br />become due; or, 2033 <br />C. Contractor or an Affiliate is the subject of a civil or criminal judgment or order entered by a Federal, State, 2034 <br />Alameda County, regional, or local agency for violation of a law that may affect performance under this 2035