Laserfiche WebLink
Mike Tassano January 31, 2025 <br />Page 33 of 37 <br />to LOS D or better at Santa Rita Road/Stoneridge Drive or Santa Rita Road/Valley Road, and <br />deteriorates traffic delay to LOS E or worse at the new intersection 4 (El Charro Road/Stanley <br />Boulevard) and intersection 5 (El Charro Road/Stoneridge Boulevard). On average, the two-lane <br />extension yields approximately half of the delay reductions that the full extension produces. <br />Comparing both extension alternatives, a partial extension of El Charro Road would yield smaller <br />benefits than a full extension, resulting in about half of the average delay reduction. Under this <br />scenario, no new intersections operate at unacceptable conditions, but the extension would have <br />an impact on traffic along Busch Road. An extension of El Charro Road as a two-lane roadway <br />would also result in about half of the average delay reduction compared to the four-lane <br />extension, with intersections such as El Charro Road at Stanley Boulevard, and El Charro Road at <br />Stoneridge Boulevard, reaching unacceptable LOS conditions. Overall, the analysis suggests a full <br />four-lane extension of El Charro Road connecting to Stanley Boulevard is warranted. <br />Travel Time Assessment <br />The intersection operations analysis presented for the alternatives above has been used to <br />estimate travel times along three key routes that would be affected by the extension: <br />• Main Street/Santa Rita Road between Bernal Avenue and Stoneridge Drive <br />• First Street/Stanley Boulevard between Bernal Avenue and Valley Avenue <br />• El Charro Road between Stanley Boulevard and Stoneridge Drive (only for plus <br />extension scenarios) <br />The impact of each land use development (Alternatives 1 through 4) on predicted travel times is <br />modest, which is consistent with the LOS results shown earlier. On average, the increases in delay <br />produced by these developments are not greater than three seconds per intersection, which is <br />not enough to substantially impact overall travel times results. For these reasons, only the travel <br />times of Alternatives 4 through 6 are shown below. <br />Table 14 presents travel times summaries for the various extension alternatives. Table 15 <br />presents the difference in travel time impacts across these alternatives. These scenarios include all <br />four project land uses.