City of Pleasanton Sewer Capital Implementation Plan20-Year Plan -- Scenario 2 Projects Funded By Priority
<br />Long Term
<br /> Capital Projects Notes Estimated Total
<br />Capital Cost FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30-31 FY 31-32 FY 32-33 FY 33-34 FY 34-35
<br />FY 35/36 -
<br />FY 44/45
<br />Existing
<br />Customers
<br />Future
<br />Customers
<br />Priority A - Capacity & Reliability Improvement Projects
<br />Project 1B: Upsize Sunol Blvd Sewers preferred alt $1,600,000 790,000$ 810,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 1,600,000$ -$
<br />Project 2A: Bernal Ave Pipe Bridge preferred alt $3,330,000 -$ 400,000$ 2,930,000$ -$ -$ -$ -$ -$ -$ -$ -$ 3,330,000$ -$
<br />Project 3: Upsize Pipes downstream of Stoneridge Mall $3,660,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 3,660,000$
<br />Project 4A: East Pleasanton Capacity Project A (Kiewit and Arroyo
<br />Lago)Note 1 $2,972,000 -$ -$ -$ -$ 222,275$ -$ -$ -$ -$ -$ -$ 222,275$ 2,749,725$
<br />Project 4B: East Pleasanton Capacity Project B (Amazon, East
<br />Lakes, Site H)Note 2 $4,314,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 4,314,000$
<br />Priority A - Lift Station Projects
<br />LS-02, -07, -08, -10 Improvements Note 3 $1,420,000 -$ -$ -$ 710,000$ 710,000$ -$ -$ -$ -$ -$ -$ 1,420,000$ -$
<br />LS-04, -12, -13, -15 Improvements Note 3 $940,000 -$ -$ 470,000$ 470,000$ -$ -$ -$ -$ -$ -$ -$ 940,000$ -$
<br />LS-05 Full Replacement Project Note 4 $6,120,000 -$ -$ 810,000$ 5,310,000$ -$ -$ -$ -$ -$ -$ -$ 6,120,000$ -$
<br />EARS and EALS Condition Assessment, Capacity Evaluation, and
<br />Predesign $500,000 166,700$ 166,700$ 166,700$ -$ -$ -$ -$ -$ -$ -$ -$ 500,000$ -$
<br />Generator Replacement - Sewer and Storm Note 5 $9,860,000 150,000$ 1,710,000$ -$ 1,000,000$ 3,000,000$ -$ 1,000,000$ 3,000,000$ -$ -$ -$ 9,860,000$ -$
<br />Priority A - Condition Assessment Projects
<br />Pipeline Replacement (1-2 mile of system)Note 6 $12,900,000 -$ 900,000$ 6,000,000$ 3,000,000$ 3,000,000$ -$ -$ -$ -$ -$ -$ 12,900,000$ -$
<br />Amberwood Siphon $3,330,000 -$ 270,000$ 3,060,000$ -$ -$ -$ -$ -$ -$ -$ -$ 3,330,000$ -$
<br />Priority A - Annual Sewer System Improvements for Resurfacing $1,400,000 -$ 350,000$ 350,000$ 350,000$ 350,000$ -$ -$ -$ -$ -$ -$ 1,400,000$ -$
<br />Large Diameter Inspection Study $150,000 -$ 150,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 150,000$ -$
<br />Denker Road Sewer Replacement $1,650,000 150,000$ 1,500,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 1,650,000$ -$
<br />Cathodic Protection and I&I Studies $150,000 -$ 150,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ 150,000$ -$
<br />Cathodic Protection Installation $18,000,000 -$ -$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 10,000,000$ 18,000,000$ -$
<br />Force Main Desktop Analysis and Inspections $704,000 104,000$ 300,000$ 300,000$ -$ -$ -$ -$ -$ -$ -$ -$ 704,000$ -$
<br />$73,000,000 1,360,700$ 6,706,700$ 15,086,700$ 11,840,000$ 8,282,275$ 1,000,000$ 2,000,000$ 4,000,000$ 1,000,000$ 1,000,000$ 10,000,000$ 62,276,275$ 10,723,725$
<br />Priority B - Lift Station Projects
<br />Health and Safety Signage $10,000 -$ -$ -$ -$ -$ -$ 10,000$ -$ -$ -$ -$ 10,000$ -$
<br />EALS R&R Note 7 $4,000,000 -$ -$ -$ -$ -$ 520,000$ 3,480,000$ -$ -$ -$ -$ 4,000,000$ -$
<br />EARS LS Note 7 $8,412,000 -$ -$ -$ -$ -$ -$ -$ -$ 1,093,560$ 7,318,440$ -$ 8,412,000$ -$
<br />EARS LS Piping Note 7 $1,647,000 -$ -$ -$ -$ -$ -$ -$ 214,110$ 1,432,890$ -$ -$ 1,647,000$ -$
<br />LS-03, -09, 11 Abandonment Note 8 $600,000 -$ -$ -$ -$ -$ -$ -$ 78,000$ 522,000$ -$ -$ 600,000$ -$
<br />LS-06 Major Rehabilitation Note 9 $2,890,000 -$ -$ -$ -$ -$ -$ 375,700$ 2,514,300$ -$ -$ -$ 2,890,000$ -$
<br />LS-08 Major Rehabilitation Note 9 $3,120,000 -$ -$ -$ -$ -$ 405,600$ 2,714,400$ -$ -$ -$ -$ 3,120,000$ -$
<br />LS-07 Major Rehabilitation Note 9 $3,700,000 -$ -$ -$ -$ -$ -$ 481,000$ 3,219,000$ -$ -$ -$ 3,700,000$ -$
<br />Priority B - Condition Assessment Projects
<br />Priority B - Pipeline Replacement (1-2 mile of system)Note 6 $15,000,000 -$ -$ -$ -$ -$ 3,000,000$ 3,000,000$ 3,000,000$ 3,000,000$ 3,000,000$ -$ 15,000,000$ -$
<br />Priority B - Large Diameter Pipe and Force Main Rehab Note 10 $6,000,000 -$ -$ -$ -$ -$ 2,000,000$ 2,000,000$ 2,000,000$ -$ -$ -$ 6,000,000$ -$
<br />Priority B - Sewer Siphon Replacement Note 10 $3,330,000 -$ -$ -$ -$ -$ -$ -$ 432,900$ 2,897,100$ -$ -$ 3,330,000$ -$
<br />Force Main Desktop Analysis and Inspections Note 11 $750,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ 750,000$ -$ 750,000$ -$
<br />Priority B - Annual Sewer System Improvements for Resurfacing Note 10 $1,750,000 -$ -$ -$ -$ -$ 350,000$ 350,000$ 350,000$ 350,000$ 350,000$ -$ 1,750,000$ -$
<br />$51,209,000 -$ -$ -$ -$ -$ 6,275,600$ 12,411,100$ 11,808,310$ 9,295,550$ 11,418,440$ -$ 51,209,000$ -$
<br />Priority C - Lift Station Projects11
<br />LS-02 Major Rehabilitation Note 9 $750,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $750,000 $750,000 -$
<br />LS-04 Major Rehabilitation Note 9 $810,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $810,000 $810,000 -$
<br />LS-10 Major Rehabilitation Note 9 $880,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $880,000 $880,000 -$
<br />LS-12 Major Rehabilitation Note 9 $1,230,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $1,230,000 $1,230,000 -$
<br />LS-13 Major Rehabilitation Note 9 $1,150,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $1,150,000 $1,150,000 -$
<br />LS-15 Major Rehabilitation Note 9 $710,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $710,000 $710,000 -$
<br />Priority C - Condition Assessment Projects
<br />Force Main and Large Diameter Desktop Analysis and Inspections Note 12 $1,500,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $1,500,000 $1,500,000 -$
<br />Priority C - Pipeline Replacement (1-2 mile of system)Note 6 $30,000,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $30,000,000 $30,000,000 -$
<br />Priority C - Large Diameter Pipe and Force Main Rehab Note 10 $12,000,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $12,000,000 $12,000,000 -$
<br />Priority C - Sewer Siphon Replacement Note 10 $3,330,000 -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ $3,330,000 $3,330,000 -$
<br />Priority C - Annual Sewer System Improvements for Resurfacing Note 10 $3,500,000 -$ $3,500,000 $3,500,000 -$
<br />$55,860,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $55,860,000 $55,860,000 -$
<br />$1,360,700 $6,706,700 $15,086,700 $11,840,000 $8,282,275 $7,275,600 $14,411,100 $15,808,310 $10,295,550 $12,418,440 $65,860,000 $169,345,275 $10,723,725
<br />Engineering/Administration FTE's Count 1 2 4 3 3 2 4 4 3 4 21 NA NA
<br />Engineering/Administration FTE's Cost $300,000 $600,000 $1,200,000 $900,000 $600,000 $600,000 $1,200,000 $1,200,000 $900,000 $900,000 $6,000,000 NA NA
<br />Total CIP $1,660,700 $7,306,700 $16,286,700 $12,740,000 $8,882,275 $7,875,600 $15,611,100 $17,008,310 $11,195,550 $13,318,440 $71,860,000 $169,345,275 $10,723,725
<br />Total Priority C Projects
<br />Estimated Total Capital Cost
<br />Cost Sharing
<br />Total Priority A Projects
<br />Priority B Projects
<br />Total Priority B Projects
<br />Priority C Projects
<br />Near Term Mid Term
<br />Priority A Projects
<br />Page 243 of 323
|