REGIONAL GROUNDWATER FACILITIES PROJECT <br />FEASIBILITY STUDY <br /> <br /> 34 Zone 7 Water Agency <br />December, 2025 <br /> <br /> Final production well design, pump selection, and motor sizing based on full-scale performance <br />testing; <br /> Final configuration and layout of the Tennis Park and Hansen Park well pump station facilities; <br /> Final configuration and layout of the reconfigured HCF; and <br /> Detailed construction sequencing and phasing combined with schedule considerations <br />Deferring these decisions allows for coordination with City departments, public outreach, and refinement <br />of technical assumptions while maintaining flexibility as the project advances. <br />Treatment Considerations and Future Planning <br />In addition to defining the facilities required for initial project implementation, the BODR includes a <br />planning-level evaluation of potential future treatment pathways to address longer-term water quality <br />considerations and Zone 7 water quality target goals. These considerations focus on treatment of total <br />dissolved solids (TDS), per- and polyfluoroalkyl substances (PFAS), or a combined treatment approach, <br />recognizing both current groundwater quality conditions and the potential for future regulatory or basin- <br />wide water quality changes. <br />The BODR treatment evaluation is intentionally framed as a future planning effort and documents the <br />regulatory context, treatment drivers, and conceptual treatment strategies that could be required under <br />different water quality scenarios, including blending of treatment technologies, development of <br />centralized treatment facilities, and phased implementation approaches. The BODR also identifies the <br />relative scale, operational complexity, footprint implications, and order-of-magnitude cost considerations <br />associated with these treatment pathways, without selecting or recommending a specific treatment <br />configuration at this time subject to Zone 7 future decision making. Key findings from the BODR treatment <br />evaluation include: <br /> Treatment for PFAS and/or TDS is not required for initial implementation of the groundwater <br />production facilities associated with Alternative 2, based on current water quality data from the <br />test wells; <br /> Future treatment needs, if any, would be driven by changes in regulatory requirements, long-term <br />groundwater quality trends, or Zone 7 policy direction related to water quality targets and basin <br />management objectives; <br /> Treatment strategies may differ depending on whether future needs are limited to PFAS, limited <br />to TDS, or require a combined treatment approach, with materially different capital, operational, <br />and siting implications; and <br /> Any future treatment facilities would require additional planning, environmental review, <br />stakeholder coordination, and funding considerations separate from the Phase II scope. <br />Final selection of any treatment approach, whether TDS only, PFAS only, or combined treatment, will be <br />guided by Zone 7 policy direction, evolving regulatory requirements, and confirmation of long-term water <br />quality objectives. Such decisions would occur independently of, and subsequent to, implementation of <br />the initial groundwater production facilities under Alternative 2.