Kier + Wright | Page 18 <br /># Task / Deliverable <br />Mo 1Mo 2Mo 3Mo 4Mo 5Mo 6Mo 7Mo 8Mo 9Mo 10Mo 11Mo 12 <br />1 Task 1 - Project Management & Coordination <br /> Kickoff Meeting (all team + City staff) <br /> Bi-weekly progress meetings <br /> Deliverable: Project management plan, schedule, <br /> meeting agendas, action item/decision logs <br />2 Task 2 - Existing Conditions Review & Data <br />Collection <br /> City document review + team background data <br /> Field reviews - all subconsultants <br /> Deliverable: Existing conditions memorandum <br />3 Task 3 - Survey & Base Mapping Support <br /> Compile GIS, LiDAR, NearMap, utility records - K+W <br /> Supplement with field survey crews (if needed) - K+W <br /> Deliverable: Base map (PDF + AutoCAD) <br />4 Task 4 - Design Criteria & Evaluation Framework <br /> Design all hands meeting - City staff + all subconsultants <br /> Deliverable: Design criteria memorandum <br /> + alternatives evaluation framework <br />5 Task 5 - Alignment Alternatives Development <br /> Hydraulic/geotech/dry utility input - S&W + CEG + Radius <br /> Structural concepts - Peoples Assoc + Alta Eng <br /> Horizontal/vertical geometry - K+W + TJKM iteration <br /> Conceptual landscape plans <br /> Deliverable: Alt exhibits, typical sections, cost estimates <br />6 Task 6 - Technical Evaluation of Alternatives <br /> Subconsultant discipline inputs <br /> Contractor constructability/cost input <br /> City review period <br /> Deliverable: Technical evaluation memorandum <br />7 Task 7 - Environmental & Permitting Constraints <br />Screening <br /> Desktop environmental screening - ICF <br /> Deliverable: Admin draft, draft + final <br /> Environmental Constraints Screening Memo <br />8 Task 8 - Utility, Drainage & Right-of-Way <br />Considerations <br /> Early Zone 7, PG&E, utility coordination - K+W + Radius <br /> Drainage/stormwater feasibility analysis - K+W + S&W <br /> Parcel/ROW acquisition assessment - K+W + AR/WS <br /> Deliverable: Utility/drainage/ROW exhibit + findings <br />memorandum <br />9 Task 9 - Stakeholder & Agency Coordination <br /> Quarry operators, Zone 7, UPRR, LAVTA, <br /> EBRPD, Caltrans, LAVWMA, private landowners <br /> Min. 3 meetings per key stakeholder <br /> Deliverable: Meeting materials, decision logs, coordination <br />documentation <br />10 Task 10 - Preferred Alignment Recommendation <br />& Final Documentation <br /> Preferred alignment synthesis - K+W + TJKM <br /> City review - draft preferred alignment package <br /> Plat maps + legal descriptions - K+W + AR/WS <br /> Deliverable: Final preferred alignment package, <br /> report, plat maps, presentation materials <br />ссссс <br />ссссссссссссссссссссссссссссссссс <br />1RWH6FKHGXOHLVEDVHGRQDQHVWLPDWHGPRQWKFRQWUDFWWHUP.H\VFKHGXOHULVNVLQFOXGH3* (XWLOLW\FRRUGLQDWLRQ8QLRQ3DFLILF5DLOURDGFRRUGLQDWLRQDQG=RQHHQJDJHPHQWDOORIZKLFKVKRXOGEHLQLWLDWHG <br />ZLWKLQWKHILUVWGD\V <br />El Charro Road Precise Roadway Alignment | Project Schedule <br />Milestone Deliverable DueLEGEND:Task Duration Subtask/Activity <br />сссссссссс <br />сссссссссс <br />сссссссссссссссссссссс <br />сссссссссс <br />сссссссссссссссссссссссссссссссссссссссссссссссссссссссссссссссссссс <br />сссссссссссссссс <br />ссссссссссссссссссссссссссс <br />ссссссссссссссссссссссссссссссссссссссс <br />ссссссссссссссссссссссссссссссссссссссс <br />Page 75 of 443