Laserfiche WebLink
ID Task Name Duration Start Finish PredecessorsWork Cost <br />1 Pleasanton - SCADA Standards Development 240.5 days Mon 7/27/26 Mon 6/28/27 1,240 hrs $349,693.97 <br />2 Key Milestones 0 days Mon 7/27/26 Mon 7/27/26 0 hrs $0.00 <br />3 Notice to Proceed 0 days Mon 7/27/26 Mon 7/27/26 0 hrs $0.00 <br />4 Task 1 - Project Management 221.5 days Mon 8/17/26 Tue 6/22/27 100 hrs $25,209.46 <br />5 Kickoff Meeting 4 hrs Mon 8/17/26 Mon 8/17/26 3FS+3 wks 8 hrs $2,208.16 <br />6 Project Closeout 1 wk Tue 6/15/27 Tue 6/22/27 21 2 hrs $577.03 <br />7 Task 2 - AWIA Crosswalk 55 days Mon 8/17/26 Mon 11/2/26 48 hrs $11,608.56 <br />8 2025 Assessment Review 2 wks Mon 8/17/26 Mon 8/31/26 5 8 hrs $2,088.32 <br />9 SCADA Management Plan Crosswalk 3 wks Mon 8/31/26 Mon 9/21/26 8 16 hrs $3,796.08 <br />10 Summary TM Development 6 wks Mon 9/21/26 Mon 11/2/26 9 24 hrs $5,724.16 <br />11 Task 3 - SCADA Standards Development 170 days Mon 11/2/26 Mon 6/28/27 772 hrs $182,469.59 <br />12 As-Built Documentation Review 1 mon Mon 11/2/26 Mon 11/30/26 7 32 hrs $7,472.32 <br />13 Instrumentation Standards 2 mons Mon 11/30/26 Mon 1/25/27 12 96 hrs $22,314.76 <br />14 SCADA Hardware Standards 2 mons Mon 1/25/27 Mon 3/22/27 13 100 hrs $24,161.18 <br />15 Controller Programming Standards 1 mon Mon 3/22/27 Mon 4/19/27 14 144 hrs $33,793.65 <br />16 Tagging Standards 2 wks Mon 3/22/27 Mon 4/5/27 14 78 hrs $17,963.63 <br />17 Graphical Standards 3 mons Mon 4/5/27 Mon 6/28/27 16 164 hrs $39,380.11 <br />18 Alarming Philosophy and Management 2 wks Mon 4/5/27 Mon 4/19/27 16 70 hrs $16,464.23 <br />19 HMI Database Conventions 1 wk Mon 4/19/27 Mon 4/26/27 18 20 hrs $4,585.93 <br />20 Reporting Standards 1 mon Tue 5/11/27 Tue 6/8/27 19FS+11 days48 hrs $11,747.85 <br />21 Version Control Standards 1 wk Tue 6/8/27 Tue 6/15/27 20 20 hrs $4,585.93 <br />22 Task 4 - Backup Core SCADA Relocation Basis of Design & <br />Cost Estimate <br />30 days Mon 11/2/26 Mon 12/14/26 7 80 hrs $18,020.64 <br />23 Basis of Design Development 4 wks Mon 11/2/26 Mon 11/30/26 60 hrs $13,460.32 <br />24 Cost Estimate Development 10 days Mon 11/30/26 Mon 12/14/26 23 20 hrs $4,560.32 <br />25 Task 5 - Remote Access Improvements Basis of Design & <br />Cost Estimate <br />60 days Mon 12/14/26 Mon 3/8/27 22SS+30 <br />days <br />160 hrs $38,505.82 <br />26 Existing Status Review 4 wks Mon 12/14/26 Mon 1/11/27 40 hrs $9,261.74 <br />27 Objectives and Design Criteria Development 20 days Mon 1/11/27 Mon 2/8/27 26 32 hrs $7,804.51 <br />28 Implementation Approach and Cost Estimate <br />Development <br />4 wks Mon 2/8/27 Mon 3/8/27 27 88 hrs $21,439.58 <br />29 Task 6 - OT System Monitoring Basis of Design & Cost <br />Estimate <br />30 days Mon 1/25/27 Mon 3/8/27 25SS+30 <br />days <br />80 hrs $18,879.91 <br />30 Existing Status Review 4 wks Mon 1/25/27 Mon 2/22/27 60 hrs $14,112.45 <br />31 Objectives and Design Criteria Development 10 days Mon 2/22/27 Mon 3/8/27 30 20 hrs $4,767.45 <br />32 Task 7 - As-needed Services 3 mons Mon 3/8/27 Mon 5/31/27 29 0 hrs $55,000.00 <br />7/27 <br />7/27 <br />Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul <br />Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027 Qtr 2, 2027 Qtr 3, 2027 <br />Task <br />Split <br />Milestone <br />Summary <br />Project Summary <br />Inactive Task <br />Inactive Milestone <br />Inactive Summary <br />Manual Task <br />Duration-only <br />Manual Summary Rollup <br />Manual Summary <br />Start-only <br />Finish-only <br />External Tasks <br />External Milestone <br />Deadline <br />Progress <br />Manual Progress <br />Page 1 <br />Project: Pleasanton - SCADA St <br />Date: Tue 5/26/26 <br />Docusign Envelope ID: C46F6467-48FC-8755-8247-09E863327CA7Docusign Envelope ID: A1F306CD-3D85-8219-8045-1E730ABF3862