Timeline of approval, permitting and installation <br />of the signage <br />x 12/3/24 – Sign Design Review application submitted <br />x 12/19/24 – Sign Design Review application deemed incomplete <br />x 12/2024 to 01/28/25 – Multiple staff/applicant meetings <br />x 01/30/25 – Sign Design Review application deemed complete <br />x 01/30/2025 – Sign Design Review application approval letter issued (effective date of 03/05/25) <br />x 02/20/25 to 02/21/2025 – Building Division completes their plan check (permits held until 03/05/25) <br />x 02/22/25 to 03/03/25 – Staff observes the applicant has installed the new wall, canopy, and pump signage without permits <br />03/04/2025 – City Council requests to review the Zoning Administrator approval <br />x 03/07/2025 – Unaware of the City Council request, Building Division issues the Sign Design Review permits <br />x 03/08/205 to 04/14/2025 – Staff observes the applicant has installed the monument signage with permits <br />x 04/15/2025 – City Council hearing for review of Zoning Administrator approval (Continued to May 6, 2025) <br />Planning Staff inspection <br />x Wall, Canopy, Pump Signage – In compliance <br />o Signage design and colors comply <br />o Signage dimensions comply <br />x Monument Sign – Not in compliance <br />o Sign design and colors comply <br />o Brick base and side surrounds comply <br />o Sign height does not comply <br />ƒApproved monument sign height exceeds the height of previous monument sign <br />(protrudes above the height of the existing brick surround), which was explicitly <br />not allowed per the ZA approval. <br />Page 200 of 249