Laserfiche WebLink
4 <br />Timeline of Events <br />1.November 2022 <br />•All City wells are out of service due to the detection of PFAS above advisory levels <br />•City starts purchasing its GPQ from Zone 7 at a wholesale rate <br />2.October 2023 <br />•The City Council approves the Water Supply Alternatives Study’s recommendation <br />to pursue new wells in the Bernal groundwater subbasin <br />•Establishment of The City Groundwater Supply Project, CIP No. 24174 <br />3.June 2024 <br />•City and Zone 7 enter into an agreement to evaluate the feasibility of a joint project <br />7 <br />Timeline of Events (continued) <br />1.December 2025 <br />•Study determines sufficient water yield and quality for a joint project and no <br />impact to groundwater sustainability per Zone 7 modeling <br />8 <br />2.April 2026 <br />•City cost-benefit analysis <br />recommends implementing <br />new groundwater wells <br />jointly with Zone 7 as <br />opposed to independently <br />7 <br />8 <br />Page 290 of 344