Project No. JB-569 <br />20 June 2006 <br />Revised 18 October 2006 <br />Page 8 <br />Building Pad backfill should be compacted a minimum of 90 percent relative <br />compaction at a minimum of 3 percent over the optimum moisture content <br />according to the latest ASTM test methods and procedures. <br />Buttress fill placed within the keyway must be compacted to a minimum of 95 <br />percent relative compaction at a minimum of 3 percent over optimum moisture <br />content. Fill placed above the keyway or above benched areas must be <br />compacted to a minimum of 95 percent relative compaction at a minimum of 1 <br />percent over optimum moisture content. <br />General fill and trench backfill should be compacted to a minimum of 90 percent <br />relative compaction at a minimum of 2 percent over the optimum moisture <br />content according to the latest ASTM test methods and procedures. <br />The upper 1 2 inches of pavement subgrade soils should be scarified, moisture- <br />conditioned as necessary, and recompacted to a minimum of 95 percent relative <br />compaction. <br />If pumping subgrade soils are encountered, we recommend over-excavating to <br />firm, non-yielding soil and placing recompacted fill as recommended in Section <br />6.1 .4. If non-yielding soil is not encountered within 2 feet below the proposed <br />subgrade elevation, an acceptable option is to place a woven geotextile at the <br />base of the excavation and backfill with a granular material. The geotextile should <br />consist of Mirafi 500X or an approved equivalent. A test area should be prepared <br />to evaluate the performance of the method. If anon-yielding pavement subgrade <br />is not achieved, deeper excavation may be necessary. <br />Soils that are not pumping but are determined to be too wet to properly compact <br />may be prepared by ripping the soil and allowing the soil to dry, excavating and <br />replacing, or lime treating. <br />All import fill must be compacted to a minimum relative compaction of 90 percent <br />of the maximum dry density and moisture-conditioned to a minimum of 2 percent <br />over the optimum moisture content according to ASTM test methods and <br />procedures. The import fill should be non-expansive, free of deleterious materials, <br />and meet the requirements in Table 2. <br />Samples of any proposed import fill planned for use on this project should be <br />submitted to our representative for approval and appropriate testing no less than <br />4 working days before the expected delivery to the job site. <br />K.nrbmacher Engineering, Inc. <br />