CORNERSTONE <br />C. EARTH GROUP <br />The contractor (with input from a Cornerstone representative) should evaluate the in-situ <br />moisture conditions, as the use of vibratory equipment on soils with high moistures can cause <br />unstable conditions. General recommendations for soil stabilization are provided in the <br />"Subgrade Stabilization Measures" section of this report. <br />6.8 TRENCH BACKFILL <br />Utility lines constructed within public right-of-way should be trenched, bedded and shaded, and <br />backfilled in accordance with the local or governing jurisdictional requirements. Utility lines in <br />private improvement areas should be constructed in accordance with the following requirements <br />unless superseded by other governing requirements. <br />All utility lines should be bedded and shaded to at least 6 inches over the top of the lines with <br />crushed rock (3/8-inch-diameter or greater) orwell-graded sand and gravel materials <br />conforming to the pipe manufacturer's requirements. Open-graded shading materials should be <br />consolidated in place with vibratory equipment and well-graded materials should be compacted <br />to at least 90 percent relative compaction with vibratory equipment prior to placing subsequent <br />backfill materials. <br />General backfill over shading materials may consist of on-site native materials provided they <br />meet the requirements in the "Material for Fill" section, and are moisture conditioned and <br />compacted in accordance with the requirements in the "Compaction" section. <br />l Where utility lines will cross perpendicular to strip footings, the footing should be deepened to <br />encase the utility line, providing sleeves or flexible cushions to protect the pipes from anticipated <br />foundation settlement, or the utility lines should be backfilled to the bottom of footing with sand- <br />cement slurry or lean concrete. Where utility lines will parallel footings and will extend below the <br />"foundation plane of influence," an imaginary 1:1 plane projected down from the bottom edge of <br />the footing, either the footing will need to be deepened so that the pipe is above the foundation <br />plane of influence or the utility trench will need to be backfilled with sand-cement slurry or lean <br />concrete within the influence zone. "Sand-cement slurry used within foundation influence zones <br />should have a minimum compressive strength of 75 psi. <br />6.9 PERMANENT CUT AND FILL SLOPES <br />All permanent cut and fill slopes in soil should have a maximum inclination of 2:1 <br />(horizontal:vertical)fnr slopes up to 10 feet high, Fill slopes should be overbuilt and trimmed <br />back, exposing engineered fill when complete. Refer to the "Erosion Control" section of this <br />report for a discussion regarding protection of slope surfaces. <br />6.10 SITE DRAINAGE <br />Ponding should not be allowed adjacent to building foundations, slabs-on-grade, or pavements. <br />Hardscape surfaces should slope at least 1 percent towards suitable discharge facilities; <br />landscape areas should slope at least 2 percent. Roof runoff should be directed away from <br />Ponderosa Active Adult Community Page 16 <br />132-2-1 <br />