Page 1 of 3 <br />Item #9 <br /> CITY COUNCIL AGENDA REPORT <br /> <br />December 3, 2024 <br />Public Works - Engineering Division <br /> <br />TITLE: APPROVE AN ADDITIONAL CONSTRUCTION CONTINGENCY OF $250,600 <br />FOR A TOTAL PROJECT CONTINGENCY AMOUNT OF $377,600 TO <br />CONSTRUCT BID ALTERNATIVES 1-4 FOR THE LIONS WAYSIDE AND <br />DELUCCHI PARKS RENOVATIONS PROJECT, CIP NO. 06716 <br /> <br />SUMMARY <br />The construction contract for the Lions Wayside and Delucchi Parks Renovations, CIP No. <br />06716, was approved by the City Council on September 3, 2024. The bid was awarded to the <br />lowest responsive bidder, Integra Construction Services, Inc., in the amount of $1,265,000 for <br />the base bid amount and included a contingency of $127,000 (approximately 10 percent) for <br />unforeseen yet necessary work. The project bid resulted in lower than estimated bid costs, <br />leaving a project balance of $323,510. At the time of the award, staff recommended not to <br />award the bid alternates due to the cost of Integra’s bid alternate pricing, which totaled <br />$447,000. After the contract was awarded, staff was able to value engineer and negotiate with <br />the contractor to construct the bid alternates for a total of $250,600, which would leave a <br />remaining balance of $72,860, when adding a new $50 expenditure for the project. The <br />funding for the project, including the recommended bid alternatives, is fully funded by <br />dedicated Parks Impact Fees such that money from the General Fund is not used to <br />implement this project. Construction of the bid alternates is not expected to impact the project <br />schedule. <br /> <br />RECOMMENDATION <br />Authorize the City Manager, or authorized staff, to approve and execute contract change <br />orders for an additional $250,600, for a total project contingency amount of $377,600, for the <br />bid alternate work and unforeseen yet necessary related work. <br /> <br />BACKGROUND <br />On July 17, 2024, the City received seven base bids ranging from $1,265,000 to $1,776,966 <br />for the Lions Wayside and Delucchi Parks Renovations project, CIP No. 06716. The low base <br />bid amount submitted by Integra Construction Services Inc. (Integra), in the amount of <br />$1,265,000, was approximately 19 percent lower than the Engineer’s Estimate of $1,560,000. <br /> <br />On September 3, 2024, the City Council awarded the construction contract to Integra <br />Construction Services, Inc. in the amount of $1,265,000 with a construction contingency of <br />$127,000 (approximately 10 percent). <br /> <br />DISCUSSION <br />The awarded base bid included park improvements that focused on the top priorities for Lions <br />Wayside Park, as determined during the Master Plan public outreach process; these priorities <br />included the construction of a new bandstand, a larger lawn area, retention of the majority of <br />the existing mature trees, a trail, gathering areas, and other supporting Lions Wayside Park’s <br />Page 78 of 126