Laserfiche WebLink
11 <br />• Preparation of As-Built Drawings is not included in this scope of work. <br />• Optional design services by Fehr & Peers, not included in this scope of service, but that may be completed for an additional fee to be negotiated prior to beginning work include the following: <br />o Corridor Lighting Analysis and addition of new lighting standards <br />o Signal Interconnect & Communication Plans <br />o Temporary Signal Plans for Construction Staging <br />MILESTONE SCHEDULE <br /> <br />Milestone Estimated Completion <br />NTP for Final Design October 2025 <br />Supplemental Surveys December 2025 <br />Potholing Utilities January 2025 <br />65% PS&E February 2026 <br />95% PS&E May 2026 <br />100% PS&E June 2026 <br />Bid Plans and Specifications July 2026 <br />Advertise and Award July 2026 to August 2026 <br />Start of Construction September 2026 <br /> <br />Page 37 of 323