1 <br />Regional Groundwater Facilities Project Phase 1- <br />Feasibility Study Update <br />February 3, 2026 <br />Timeline and Project Progress at a Glance <br />OCT 2023 <br />Council <br />approved: <br />Development of <br />new <br />groundwater <br />wells in the <br />Bernal subbasin <br />JUNE 2024 <br />Council Approved: <br />Agreement to <br />perform Phase 1- <br />Feasibility Review <br />on a joint project <br />City of Pleasanton <br />Cost Share NTE <br />$1,000,000 <br />NOV 2024 <br />Council Approved: <br />Amendment 1 for <br />additional scope. <br />City of Pleasanton <br />Cost Share NTE <br />$1,283,231 <br />DEC 2025 <br />Zone 7 completed: <br />1. Install three test <br />wells <br />2. Yield and water <br />quality testing and <br />verification <br />3. Groundwater <br />modeling for <br />sustainability and <br />PFAs mobilization <br />analysis. <br />4. Feasibility Study <br />5. Basis of Design <br />DEC 2024 <br />State Waterboard <br />awarded <br />$1,000,000 grant <br />to Pleasanton to <br />reimburse the City <br />for the Feasibility <br />Study effort. <br />SEPT 2022 <br />Council decision: <br />Place all wells <br />out of service <br />due to PFAs <br />detection level. <br />Wells go off line <br />effective Nov <br />2022 <br />OCT 2022 <br />Council <br />approved: <br />Initiation of <br />Water Supply <br />Alternatives <br />Study <br />Page 35 of 80