Page 2 of 3 <br /> <br />DISCUSSION <br />The project was advertised for construction bids on February 17, 2024. Sealed bids were <br />opened on March 20, 2024. A total of three bids were received, ranging from $4,183,298 to <br />$4,903,100. The lowest responsive bid was submitted by Bay Cities Paving & Grading, Inc. in <br />the amount of $4,183,298. The low bid was approximately 10 percent higher than the <br />Engineer's Estimate of $3,815,876. <br /> <br />Project work included traffic control, temporary striping, excavation of existing roadway and <br />concrete sidewalks, driveways and medians; landscaping and irrigation modification; tree <br />removal; drainage systems; installation of concrete sidewalks, curbs, driveways and sound <br />wall; cold planning of asphalt; asphalt pavement overlay; seal coating; pavement delineation; <br />modification of the lighting system; and installation of a traffic signal system. <br /> <br />Because a portion of the project was located within the State of California’s right-of-way, the <br />work was completed under a Caltrans encroachment permit. Upon completion of construction <br />activities, staff provided Caltrans with the required documentation. <br /> <br />A total of 12 contract change orders were issued during the contract term, resulting in a net <br />increase of $23,536.71, or 0.06 percent, over the original contract amount. <br /> <br />All work has been completed in accordance with approved plans and special provisions, so the <br />project is ready for final acceptance by the City Council. <br /> <br />Acceptance of the constructed public improvements will add to the City’s inventory of <br />infrastructure requiring long-term maintenance. <br /> <br />EQUITY AND SUSTAINABILITY <br />Approval of this action advances the Climate Action Plan (CAP 2.0) in transportation and land <br />use by promoting a more effective transportation system that supports walking and bicycling. <br /> <br />OUTREACH <br />Construction notices, social media posts, and project information were posted on the City’s <br />website prior to the start of construction. Construction message boards were installed two <br />weeks in advance of work on major roadways. The contractor also hand-delivered construction <br />notices to businesses and residents within and adjacent to the project area. <br /> <br />STRATEGIC PLAN ALIGNMENT <br />Approval of this action advances the citywide ONE Pleasanton Strategic Goal of Investing in <br />our Environment, Strategy 1 - Implement the Capital Improvement Program. <br /> <br />FISCAL IMPACT <br />Total funding for this project was $6,187,694. Total project expenditures were $5,084,992, <br />leaving a remaining balance of $1,102,702, as shown in Attachment 2. Staff recommends <br />returning the remaining project balance to the applicable fund balances as follows: $950,348 to <br />the Street CIP- General Fund (Fund 211) and $152,354 to the Traffic Impact Fees Fund (Fund <br />212) for future eligible projects through the CIP prioritization process. <br /> <br />Page 294 of 617