Project No. JB-569 <br />20 June 2006 <br />Revised 18 October 2006 <br />Page 14 <br />We recommend concrete slab-on-grade floors, garage floors, and exterior flatwork <br />be a minimum thickness of 4 inches. The actual slab thickness must be <br />determined by the project structural engineer. <br />Due to the expansive nature of the near surface soil, we recommend reinforcing <br />the concrete slab-on-grade floors, garage tloor, and/or exterior flatwork with a <br />minimum of either, (1) No. 4 reinforcing bars spaced at 18 inches on center, or <br />(21 with an alternate steel reinforcement as required by the project structural <br />engineer. In general, the steel reinforcement should be supported by concrete <br />dobies to maintain the minimum requirement for clearance according to the latest <br />UBC standard. The project structural engineer should determine the acceptable <br />concrete cover. Crack control joints should be located as directed by the project <br />structural engineer. <br />~ Recommendations presented in the American Concrete Institute manual should be <br />complied with for all concrete placement and curing operations. Improper curing <br />techniques and/or excessive slump (water-cement ratio) could cause excessive <br />shrinkage, cracking or curling. Concrete slabs should be allowed to cure <br />adequately before placing vinyl or other moisture sensitive floor coverings. <br />6.6 Drainage <br />It is important that foundation soils not be allowed to become saturated during or <br />after construction. Furthermore, surface water must not be allowed to pond <br />adjacent to building foundations. To preclude drainage problems, we recommend <br />continuous roof gutter for the proposed structures. It will be necessary to direct <br />all water collected from roof downspouts into closed conduits that lead to <br />acceptable discharge points away from the structures. <br />In addition, we recommend that a subdrain system be installed around the <br />perimeter of the buildings to prevent groundwater from saturating foundation <br />soils. The subdrain should consist of a perforated, rigid, PVC pipe surrounded by <br />a minimum of 12 inches of an approved, clean drain rock, wrapped completely in <br />an approved geotextile fabric. The pipe should be installed with the holes facing <br />down and sloped to drain at a minimum grade of 1 percent. The subdrain should <br />be extended with solid pipe to an acceptable discharge point. Additional <br />subdrains may be required as determined by the soils engineer during grading <br />operations. Atypical subdrain is shown on Figure 10, subdrain Detail. <br />Grades should be such that drainage is away from the structures. Water and <br />sewer utility lines should be properly installed to avoid becoming possible sources <br />~orbmacher Engineering, Inc. <br />