Access ramp construction with 15 -foot wings plus the concrete to the nearest score
<br />joint(s) shall be measured as a complete unit and shall be considered part of the access
<br />ramp construction. Additional concrete sidewalk removed as directed by the Engineer
<br />that is beyond the score joint(s) mentioned above shall be measured as part of sidewalk
<br />construction.
<br />15-05 Pae
<br />Add:
<br />Full compensation for furnishing all labor, materials, tools, equipment, and incidentals
<br />and for doing all the work involved in the construction of, center median island including
<br />nosing, sidewalk, driveway, curb and gutter, valley gutter, bulb out, ADA ramp
<br />regardless of the type or class of ramp being constructed, including but not limited to the
<br />removal and disposal of hedges, lawns, decorative rocks, AC, tying in on existing
<br />irrigation systems, adjusting existing irrigation system, installing new irrigation system,
<br />and the installation of new lawn, landscape and new concrete surfacing, asphalt
<br />pavement, resetting pavers, rebars, coordinating with fronting property owners, curb re-
<br />painting if needed, shifting the centerline of the new ramp, adjusting and coordinating the
<br />relocation of utility boxes, replacement of utility boxes if damaged during removal, re-
<br />setting of street poles and signs, re -setting of pedestrian barricades, measurement of area
<br />for proper drainage, potential enlargement at some locations of the side areas or "wing"
<br />of an access ramp construction to the nearest concrete joint/score line, etc., shall all be
<br />considered included in the various contract items of work and no additional compensation
<br />shall be allowed therefore.
<br />The contract price for Remove and Replace (R/R) Case " " (all case) ADA Ramp shall
<br />include full compensation for all work shown on project plans and these Special
<br />Provisions including but not limited to installation of fronting curb and gutter, pavement
<br />conform with HMA of standard 1 foot slot cut or as shown on the plans, the ADA domes
<br />(regardless of width), the retaining curb(s) at the back or at the sides, installation of soil
<br />and mulch, restoration, adjust utility box to grade, moving signs and the potential
<br />enlargement of the side areas up to the nearest control joints and all other associated
<br />work.
<br />The contract price for Remove and Replace (R/R) Case" "(all case) with Case C1/C2
<br />Blended Transition ADA Ramp shall include full compensation for all work shown on
<br />project plans and these Special Provisions including but not limited to installation of
<br />fronting curb and gutter, pavement conform with HMA of standard 1 foot slot cut or as
<br />shown on the plans, the ADA domes (regardless of width), the retaining curb(s) at the
<br />back or at the sides, restoration, adjust utility box to grade, moving signs and the potential
<br />enlargement of the side areas up to the nearest control joints and all other associated
<br />work.
<br />The contract price for Remove and Replace (R/R) Case " " (all case) with Oversize (OS)
<br />ADA Ramp shall include full compensation for all work shown on project plans and
<br />these Special Provisions including but not limited to installation of fronting curb and
<br />gutter, pavement conform with HMA of standard 1 foot slot cut or as shown on the plans,
<br />the ADA domes (regardless of width), the retaining curb(s) at the back or at the sides,
<br />installation of soil and mulch, restoration, adjust utility box to grade, moving signs and
<br />Annual Curb & Gutter for Street Resurfacing Project, CIP No.25509 Page 57