Laserfiche WebLink
City of Pleasanton | Stormwater System Management Plan | PWD 25.601 | PAGE 19  <br />Flood Risk = Likelihood x Consequence  <br />Task 5 | Development of a Capital Improvement Plan <br />A capital improvement plan (CIP) will be developed to determine locations, schedules, and resources (land, labor, capital) for agency‐  <br />wide improvement projects identified to reduce flood risks and restore drainage facility useful life.  <br />Task 5.1 – Risk for Condition and Capacity Deficiencies <br />Wood Rodgers will develop improvement project prioritization criteria based on flood risk, cost‐effectiveness, social equity benefits,  <br />health and safety, and traffic interruption considerations. The ranking developed from the prioritization criteria will then be used to  <br />develop an implementation schedule for a 10‐year CIP. The practice is to maximize the involvement of City staff in all critical decisions  <br />in selecting appropriate criteria and prioritizing projects. A Workshop with City staff shall be conducted to discuss and gain buyoff on  <br />the criteria and methodology.  <br />FLOOD RISK <br />Where numerous projects are required to address deficiencies, we have implemented more formal risk models  <br />that quantify the likelihood of capacity exceedance/failure and the associated consequences. Projects intended  <br />to address the highest risks in the storm drain system with the lowest cost will be given the highest priority in  <br />the CIP.  <br />▪The likelihood of flooding based on the simulated facility capacity <br />▪The associated consequences measured in flood damages or floodplain areas <br />The drainage facility flood risk for each of the deficient systems is calculated using the following formula: <br />The calculated flood risks provide standard and quantifiable values to assist the City to prioritize improvement  <br />projects for capacity deficient drainage systems. Wood Rodgers will use the calculated flood risks and the  <br />respective improvement project capital costs to determine the cost effectiveness for the major deficient  <br />drainage systems for improvement project prioritization.  <br />This flood risk model provides floodplain extents, flood frequencies, flood damages, and benefit‐cost ratios  <br />(BCR) that can be used to support future flood mitigation grant applications.  <br />SOCIAL EQUITY <br />In addition to flood risk and cost‐effectiveness considerations, Wood Rodgers proposes incorporating equity  <br />benefits into improvement project prioritization. Prioritizing projects with equity considerations promotes fair  <br />resource allocation, enhances social cohesion, garners public support, ensures legal compliance, and fosters  <br />long‐term economic benefits. The equity framework consists of six themes that cover broad areas of people’s  <br />lives, including: 1) economy; 2) education; 3) public health; 4) housing; 5) public safety; and 6) neighborhood  <br />and civic life.  <br />TRAFFIC INTERRUPTION <br />Traffic interruption is another risk and a source of economic loss that local communities endure during flooding  <br />events. The risks of emergency access isolation, vehicular accidents, and pedestrian access restrictions are  <br />critical concerns for the community. Lost wages and business interruptions represent additional economic  <br />impacts. A metric that has been used and accepted by FEMA in grant applications is Average Daily Traffic (ADT)  <br />counts. Flooding in areas with higher ADT values has a greater impact on transportation than does flooding in  <br />areas with lower ADT values. A higher ranking will be assigned to deficient storm drain systems with a high ADT,  <br />while a lower ranking will be assigned to those with a low ADT.  <br />In addition to the prioritization criteria above, Wood Rodgers will work with the City’s staff to assess the environmental permitting  <br />requirements, rights‐of‐way, encroachment permits, and utility conflicts for the improvement projects.  <br />Deliverable(s): Project flood risk | Criteria and Methodology Workshop  <br />EXHIBIT A <br />Docusign Envelope ID: DF86282A-2A84-404C-9F8A-A035AEFBCFF8