EVALUATION OF GROUNDWATER SUPPLY ALTERNATIVES WITHIN BERNAL SUBBASIN <br />APRIL 2026 / FINAL / CAROLLO <br />CITY OF PLEASANTON 4 <br />Table 1 Alternative 1 City Distribution System Improvements <br />Improvement <br />Number(1) <br />Type of <br />Improvement <br />Size (inches) Length (lf) Cost Share <br />(City Percentage) <br />Capital Cost, City <br />Share ($)(2) <br />TO-8 Turnout N/A N/A City (100%) 4,270,000(3) <br />F-1 Pipe 24 5,250 City (100%) 3,810,000 <br />F-2 Pipe 24 310 City (100%) 220,000 <br />F-6 Pipe 16 3,800 City (100%) 2,090,000 <br />F-7 Pipe 16 3,450 City (100%) 1,900,000 <br />Notes: lf – linear feet. <br />(1) The information presented in this table is from Akel’s Hydraulic Analysis Results Package No. 1 (Revised) (Akel, November <br />2025). <br />(2) Costs provided in Akel’s Hydraulic Analysis Results Package No. 1 are from April 2023. According to Engineering News <br />Record’s 20-City Cost Index, market escalation from April 2023 to January 2026 is 6.6 percent. The costs provided in this <br />table are escalated to 2026 dollars and rounded to the nearest ten thousand. <br />(3) The capital cost for TO-8 was estimated by Carollo as detailed in Appendix B and supersedes costs provided by Akel. <br />The City and Akel identified that a new turnout (Turnout 8) is required to connect to Zone 7’s transmission <br />system to meet future demand conditions and provide improved reliability to existing Turnout 5. The <br />capacity of Turnout 8 is assumed to match the capacity of Turnout 5, which is up to 7,000 gallons per <br />minute (gpm) and would be located on City-owned property near the intersection of Vineyard Avenue <br />and Bernal Avenue as shown in Figure 2. The turnout will be located downstream of a tee connection to <br />Zone 7’s existing 36-inch water main in Vinyard Ave. The turnout consists of a below ground concrete <br />vault containing a flow control valve, flow meter, check valve, and isolation valves as shown in Figure 3. <br />This vault will be owned and operated by Zone 7, but the City is responsible for the cost of its <br />construction. Downstream of the turnout, the water main becomes City property. The example schematic <br />layout and configuration of the turnout, shown in Figure 3, was provided by Zone 7. Connection to the <br />City’s distribution system will be located downstream of the turnout vault at an existing 18-inch stub out <br />as shown in Figure 2. The turnout will also need to include fluoridation facilities owned and operated by <br />the City. The fluoridation chemical storage and pumping equipment will be located in a concrete masonry <br />unit building adjacent to the turnout. <br />The property identified for Turnout 8 is currently zoned Planned Unit Development with Residential <br />Design (residential). To construct the new turnout, the City’s planning department recommends rezoning <br />the property to public facilities. The City has determined it is feasible to rezone the property but would <br />require approval by the Planning Commission and City Council. The City estimates the rezoning process <br />would require 4 months.