Laserfiche WebLink
r'roject No. JB-569 <br />20 June 2006 <br />Page 8 <br />All import fill must be compacted to a minimum relative compaction of 90 percent <br />of the maximum dry density and moisture-conditioned to a minimum of 2 percent <br />over the optimum moisture content according to ASTM test methods and <br />procedures. The import fill should be non-expansive, free of deleterious materials, <br />and meet the requirements in Table 2. <br />Samples of any proposed import fill planned for use on this project should be <br />submitted to our representative for approval and appropriate testing no less than <br />4 working days before the expected delivery to the job site. <br />Table 2 <br />IMPORTED MATERIAL REQUIREMENTS <br />Sieve Size Percent Passing <br />6 inches 1150 mm) 100 <br />4 inches (100 mm) 95 - 100 <br />#200 5-25 <br />Plasticity (PU = 12 or less <br />Liquid Limit ILL) = 30 or less <br />Clay soils should not be allowed to dry out and crack. Any dried clay soils should <br />be wetted until they reach acceptable moisture contents or they can be excavated <br />and replaced with acceptable properly compacted fill. <br />6.1.5 Cut Slopes <br />Cut slopes should not be steeper than 2H:1 V. We recommend all cut slopes be <br />evaluated by our engineering geologist during earthwork operations. If adverse <br />bedding or other zones of weakness either in the bedrock or soil materials are <br />encountered additional recommendations will be provided. <br />6.1.6 Fill Slopes <br />Fill slopes should not be steeper than 2H:1 V. For fill placed on native or cut <br />slopes or reconstructing a slope area, we recommend that a keyway be excavated <br />at least 3 feet into the underlying competent bearing soil or bedrock at the toe of <br />the proposed fill as shown on Figure 9. The bottom of the keyway must be a <br />minimum width of 10 feet and be sloped a minimum of 2 percent downward into <br />the hillside. The total depth and width of the keyway and the extent of the fill <br />slope configuration will be determined in the field during grading by our <br />representative. <br />A subdrain system must be installed in the keyway to collect migrating water. <br />The subdrain system should consist of '/Z by 3/<-inch clean drain rock wrapped in <br />~Korbmacha~rptOgedeelrt~r~ge(O~extlle with a perforated rigid 4-inch-diameter PVC (sch. 80) <br />